OEE – OOE – TEEP explained

Q: What is the difference between the OEE, OOE and TEEP measurements? 

Overall Equipment Effectiveness measures a machine’s availability, performance and quality in order to visually display all the losses that occur on this machine. So how do OOE and TEEP measurements differ from this?

Arno Koch •  The three measures are all visualising effectiveness losses.

The only difference between OEE, OOE and TEEP is the ‘maximum time’ that is used in each calculation.

In other words, the only changing variable between these three calculations is the maximum time that is available for a machine to run. They all take availability, performance and quality into account.

Total Effective Equipment Performance Considers maximum time to be All Available Time – that is 24 hours, 365 days a year.

Overall Operations Effectiveness takes unscheduled time into account, looking at Total Operations Time as a maximum.

Overall Equipment Effectiveness looks at the Potential Production time as a maximum, without calculating time that has been unscheduled.

OEE_OOE_TEEP

Introduction: what is behind those KPI’s ?

In the ideal world, manufacturing equipment would be adding value all the time, at theoretical maximum speed, in precisely the desired quality.
So, if we want to know why our equipment is not ideal, there are 4 questions to be answered:

  1. Was the machine scheduled to run or not? The time it is scheduled to perform is also referred to as shift-time or loading time.
  2. When the machine was scheduled to produce, for what reasons was it not running? What was stopping the conversion process?
  3. When it was running, how come it was not running at theoretical maximum speed? What was reducing its speed?
  4. In the produced output; what quality defects occurred?

‘Scheduled’ versus ‘not scheduled’: Loading Rate

Please note: 
'Scheduled Time' is also referred to as 'Loading Time'

So first we determine: How much of the total time was the machine scheduled to run?

This is the Loading Rate:

Loading rate = Scheduled Time / Calendar Time

loadingfactor

Please note: 
Breaks and other waiting is INCLUDED in the loading-time: 
It is part of the operation; 
theoretically the machine could run!

Un-scheduled

Once the machine is scheduled, it will usually be operated in a certain shift regime. However sometimes it will be unscheduled again. Regular shift time can be unscheduled for several reasons; ie there is no demand, R&D needs to runs some tests etc. Those reasons are beyond the scope of the production-team.

Please do not confuse un-scheduled with 
not-scheduled or unplanned!

‘Planned’ versus ‘Unplanned’

Preventive maintenance usually is planned. Corrective Maintenance is usually unplanned. Change-overs may be planned, so are breaks.

Of course we rather see planned waiting times than unplanned ones. Yet to the OEE it does not make a difference. The machine waits, is not effective. For purposes of analysing- or visualising the losses it may be interesting to distinguish ‘planned’ and ‘unplanned’ stops, yet planned or unplanned does NOT results in a different OEE, OOE or TEEP

Running or not: Availability

A machine is scheduled (‘Loaded’) in order to produce. When the machine is scheduled, we measure: “Was it having output, regardless the speed and the quality?”.
The relation between the time the machine was having output and the time it could have produced output is called

Availability rate: The percentage of time the machine was available, was able to produce output.

Performance

Whenever the machine is running, thus really produces output, we determine how much, or how fast, the output was produced.

The ratio between the theoretical quantity of output while running, versus what actually came out, is the Performance rate.

Quality

From everything that came out, it is determined whether it was meeting the quality as expected. Was the output within the specification?

The ratio between the total actually produced output and the good output is called the Quality rate.

There are several KPI’s possible around those three rates. The main difference is the timeframe that is been considered while looking at availability.

In the end they all those KPI’s want to know: How much good product came out versus how much could it have been produced? And here is the crux: it all depends on what time frame is considered.
If we look at a years’ production; is this now based on 365 days of 24 hrs? Or is it only the time of all the shifts we would have scheduled? Or only the actually scheduled shifts? Or do we only consider the time we planned the machine to run within the scheduled shifts?

The KPI cascade

Let’s break it down to the core.

TEEP

If we want to know the real utilization, the real effectiveness of our equipment, we look at the amount of good product produced versus what could have been produced if there would have been no restraint at all.

This is what TEEP does. It takes 24hrs of 365 days a year as potential production time.
A well defined TEEP (and this also applies to OOE and OEE) takes the theoretical output as a maximum for performance and OTIF (so within specification AND on time) as a quality limit.

TEEP calculates availability as a ratio between the TOTAL calendar-time during the measurement versus the time the machine was actually having output in that period.

So in a 1-shift operation of 40 Hrs during an 168 week, the availability can be theoretically no more than 40/168= 23% (assuming OEE=100%). TEEP now shows clearly that the equipment is sleeping at least 77% of its life time due to the fact it is not scheduled to produce. In this example TEEP = Loading Rate.

So one could also say:

TEEP = Loading Rate x Availability Rate x Performance Rate x Quality rate   …or

TEEP = Loading Rate x OEE

Overall Operations Effectiveness (OOE)

For those working in the daily operation, TEEP uses a timeframe that is ‘too wide’. The operations management is interested in the effectiveness of the equipment during operations time. So the first filter to apply is to take out all the time that the equipment was not scheduled anyway.
In other words:

OOE uses all regular shift time as the time-frame.

Overall Equipment Effectiveness (OEE)

This is the KPI for the shopfloor-team.

OEE relates the actual good output versus the ultimate potential good-output while the machine was scheduled to run. (So during the actually scheduled shift time).

Example

What if we have a line that runs one shift (8 hrs) and there is a production plan is for that time; what happens with the other two shifts? In theory the line is available to run 3 shifts, but its been used for just one shift.

  • There is ONE shift scheduled: The OEE will be measured over that shift. Non scheduled time (two shift that day, plus the missing shifts in the weekend) are not included.
  • There is no unscheduled time (time taken out of the scheduled time) so the OOE equals the OEE.
  • The TEEP will be calculated over the TOTAL time, so the scheduled plus the not scheduled shift: it will be fundamentally lower.

See also:

Tagged , , . Bookmark the permalink.